Mining · 2024

Synchronous mill drive replacement, copper concentrator

Replacement of a 4 MW synchronous mill drive within the existing foundation and shutdown window.

Rating
4 000 kW
Voltage
10 000 V
Speed
600 rpm
Shutdown window
21 days
The problem

The original machine was out of support and the OEM would not quote a like-for-like replacement. The concentrator had a fixed 21-day shutdown and no budget for civil work, so any replacement had to bolt to the existing foundation and couple to the existing pinion.

What was done

A dimensional survey established the foundation bolt pattern, shaft height and coupling geometry. A salient-pole machine was designed inside the original envelope with a modern Class F insulation system and brushless excitation, allowing the plant to remove the old brush gear and its maintenance requirement.

Outcome

The machine was installed and commissioned inside the shutdown window. Measured efficiency was 1.4 points above the machine it replaced, with no change to foundations, coupling or the existing protection scheme.